This lithium project is still in the exploration phase.
NOW is the time to stop it!
-
Current Status
Protest walk planned for September 25-28
Waiting for BLM decision on Exploration Project Phase 3
Cholla Ranch caretaker has observed other drilling farther from the site
-
July 2021
Environmental Assessment comment period closed
-
June 2021
Environmental Assessment public comment period extended one additional month.
-
May 2021
Environmental Assessment comment period extended one month
-
March 2021
BLM released Environmental Assessment for Exploration Project Phase 3
Public comment period for EA began
-
November 2020
BLM denied Tribe's request to participate as cooperating agency
-
June 2020
Bureau of Land Manage-ment (BLM) invited Hualapai Tribe to participate in consultation
Tribe accepted offer and requested to serve as cooperating agency
BLM did not respond
-
2018-2019
Big Sandy Inc. started exploratory drilling to estimate how much lithium (and $$) they could mine
Drilled 12 and 37 holes in Exploration Phases 1 & 2
No tribal or community consultation, no environmental or cultural impact assessment
Legal under 1872 Mining Law